42. For the duration of the project, the promoter must keep a register of the modifications made to the baseline scenario and project scenario, including in particular a summary description of the main modifications made to the information and data entered into the CBM-CFS software and the calculation tool for the initial characterization and the updating of the baseline scenario and project scenario.
The information in the register must be kept for a minimum period of 7 years from the project end date and be made accessible, for consultation, by the persons responsible for verifying the project.
M.O. 2022-11-17, s. 42.
In force: 2022-12-29
42. For the duration of the project, the promoter must keep a register of the modifications made to the baseline scenario and project scenario, including in particular a summary description of the main modifications made to the information and data entered into the CBM-CFS software and the calculation tool for the initial characterization and the updating of the baseline scenario and project scenario.
The information in the register must be kept for a minimum period of 7 years from the project end date and be made accessible, for consultation, by the persons responsible for verifying the project.
M.O. 2022-11-17, s. 42.